Project Executed

A PARTIAL LIST OF VERIFIABLE PROJECTS UNDERTAKEN BY ENVIRON-WASTE NIGERIA LIMITED


01. Production of proposal and scope of work on Waste Management System in accordance with ISO14001 principles for the Bonny Oil Terminal
Duration: March - April 2000
Client: Shell Petroleum Development Company (SPDC)

02. Production of proposal for Waste Management System in line with ISO14001 Environmental management Systems
Duration: April 2004
Client: Schlumberger Nigeria Limited, Trans Amadi Ind. L/Out, Port Harcourt

03. Design and construction of 2 oil/water separators
Duration: November 2001
Client: Baker Hughes (Inteq) Nig. Ltd., Trans Amadi Ind. L/Out, Port Harcourt

04. Monitoring of effluent from Baker Hughes facilities at Trans Amadi and Onne FOT
Duration: January 2002 to present date
Client: Baker Hughes (Inteq) Nig. Ltd., Trans Amadi Ind. L/Out, Port Harcourt

05. Drilling of 10 boreholes for the monitoring of underground water along the effluent channel and some chosen locations within the Bonny Oil terminal including one hole drilled in Bonny town as a control for SPDC at Bonny Oil Terminal
Duration: October 2001 to April 2002
Client: Shell Petroleum Development Company (SPDC)

06. Implementation of the contract for the Waste Management System (11 locations) and the maintenance of Oil/Water separators at the Blue Base and Drilling & Measurement Base
Duration: Jan 2002 to current date
Client: Schlumberger Nigeria Limited, Trans Amadi Ind. L/Out, Port Harcourt

07. Pest control contract at construction sites (LNG & LPG) and National residents for CBI and JBN respectively in Nigeria LNG expansion project, Bonny Island
Duration: Completed
Client: Nigeria LNG

08. Remediation of two abandoned underground petrol storage tanks location at the Blue Base of Schlumberger Nigeria Limited
Duration: June 2001
Client: Schlumberger Nigeria Limited, Trans Amadi Ind. L/Out, Port Harcourt

09. Remediation of oil spillage sites at Cawthorne Channel flow station
Duration: April 2003
Client: Shell Petroleum Development Company (SPDC)

10. Clean-up and disposal of spilled drilling mud
Duration: April 2003
Client: Baker Hughes (Inteq) Nig. Ltd., Trans Amadi Ind. L/Out, Port Harcourt

11. Production of Environmental Audit Report
Duration:Completed
Client: OKMAS Nig. Ltd., Port Harcourt

12. Production of Environmental Assessment Report (EAR) for Baker Hughes Nig. Ltd. at her Onne FOT and FLT facilities
Duration: Completed
Client: Baker Hughes (Inteq) Nig. Ltd., Trans Amadi Ind. L/Out, Port Harcourt

13. Disposal of electromagnetic tapes and housing
Duration: Completed
Client: Western Geco Nig. Ltd., Port Harcourt

14. Consultant services: EIA protection for Oza/Ohuru seismic survey activity
Duration:
Client: